Berths 1, 2 & 3 at Rottnest Island are comprised of Sheet Piling for the main wharf deck and the twenty (20) x Fender piles are 200mm H-piles. The original section of sheet piling was installed in 1962 with a 137-foot extension commenced 5 years later. Preservation works planned to extend the service life of the Sheet Piling and Fender Piles including painting to preserve the steel within and above the tide zone and additional sacrificial anodes to reinstate Cathodic Protection (CP) below water.
Public award record
Rottnest Island Authority - Replacement of Anodes to Sheet Piles - Berths 1-3
- Location
- Perth Metropolitan
- Public buyer
- Rottnest Island Authority
AWARD DETAILS
- Buyer
- Rottnest Island Authority
- State
- WA
- Published
- Contract start
- —
- Category
- Specialized trade construction and maintenance services - (100%)
- Value
- $243.2k
- Value type
- (Estimate)
- Procurement method
- Invited Tender
- Record updated